Current system
See: Generation for more details of the current generation systems
White mountain (eagle creek)
Present value of capital cost: $28,622,672
Lifetime energy cost savings: $-3,265,128
Net lifetime savings: $-31,887,801
Benefit-cost ratio: -0.1
Proposed nameplate capacity: 200 kW
Expected yearly generation: 690,221 kWh/year
Phase: Reconnaissance
Upfront capital cost: $29,140,234
Estimated hydro penetration level: 73.32%
source: link
Golovin (east tributary and upper cheenik creek) -- Cheenik Creek, Upper
Present value of capital cost: $21,622,870
Lifetime energy cost savings: $-3,302,463
Net lifetime savings: $-24,925,333
Benefit-cost ratio: -0.2
Proposed nameplate capacity: 164 kW
Expected yearly generation: 392,000 kWh/year
Phase: Reconnaissance
Upfront capital cost: $22,013,860
Estimated hydro penetration level: 41.64%
source: link