Current system

See: Generation for more details of the current generation systems

Modeled transmission project

Capital cost (total): $15,537,166

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-9,186,260

Net lifetime savings: $-24,723,425

Benefit-cost ratio: -0.6

Nearest community: Angoon

Distance: 31 miles

Maximum savings: $0.06/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.