Current system

See: Generation for more details of the current generation systems

Modeled transmission project

Capital cost (total): $16,413,538

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-10,983,585

Net lifetime savings: $-27,397,123

Benefit-cost ratio: -0.7

Nearest community: Quinhagak

Distance: 32 miles

Maximum savings: $0.10/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.