Current system

See: Generation for more details of the current generation systems

Modeled transmission project

Capital cost (total): $5,555,070

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-2,889,307

Net lifetime savings: $-8,444,377

Benefit-cost ratio: -0.5

Nearest community: Kwigillingok

Distance: 11 miles

Maximum savings: $0.04/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.