Current system

See: Generation for more details of the current generation systems

Modeled transmission project

Capital cost (total): $17,627,341

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-11,415,769

Net lifetime savings: $-29,043,110

Benefit-cost ratio: -0.6

Nearest community: Tununak

Distance: 35 miles

Maximum savings: $0.00/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.