Current system
See: Generation for more details of the current generation systems
Sand point (unnamed stream, site #2) -- Unnamed creek
Present value of capital cost: $3,137,569
Lifetime energy cost savings: $433,330
Net lifetime savings: $-2,704,239
Benefit-cost ratio: 0.1
Proposed nameplate capacity: 39 kW
Expected yearly generation: 215,069 kWh/year
Phase: Reconnaissance
Upfront capital cost: $3,194,303
Estimated hydro penetration level: 5.52%
source: link
Sand point -- Humbolt Creek
Present value of capital cost: $6,578,657
Lifetime energy cost savings: $28,167
Net lifetime savings: $-6,550,490
Benefit-cost ratio: 0.0
Proposed nameplate capacity: 70 kW
Expected yearly generation: 303,000 kWh/year
Phase: Reconnaissance
Upfront capital cost: $6,697,614
Estimated hydro penetration level: 7.77%
source: link