See: Generation for more details of the current generation systems
Modeled transmission project
Capital cost (total): $1,826,006
Capital cost (cost per mile): $500,000/mile
Lifetime energy cost savings: $7,628,040
Net lifetime savings: $5,802,034
Benefit-cost ratio: 4.2
Nearest community: Togiak
Distance: 4 miles
Maximum savings: $0.38/kWh
This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.