Current system

See: Generation for more details of the current generation systems

Chikuminuk lake

Present value of capital cost: $309,005,902

Lifetime energy cost savings: $359,855,683

Net lifetime savings: $50,849,781

Benefit-cost ratio: 1.2

Proposed nameplate capacity: 13,400 kW

Expected yearly generation: 88,700,000 kWh/year

Phase: Reconnaissance

Upfront capital cost: $314,593,420

Estimated hydro penetration level: 208.80%

source: link

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from the installation of new hydropower infrastructure. Requires that at least a reconnaissance-level hydropower study has been completed for the community.