See: Generation for more details of the current generation systems
Modeled transmission project
Capital cost (total): $17,211,691
Capital cost (cost per mile): $500,000/mile
Lifetime energy cost savings: $-13,862,486
Net lifetime savings: $-31,074,177
Benefit-cost ratio: -0.8
Nearest community: Rampart
Distance: 34 miles
Maximum savings: $0.61/kWh
This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.