Modeled transmission project

Capital cost (total): $14,756,203

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-15,214,101

Net lifetime savings: $-29,970,303

Benefit-cost ratio: -1.0

Nearest community: Pilot Station

Distance: 29 miles

Maximum savings: $0.02/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.