Modeled biomass cordwood project

Capital cost: $1,383,777

Lifetime energy cost savings: $50,997

Net lifetime savings: $-1,332,779

Benefit-cost ratio: 0.0

Proposed max capacity: 2,265,226 mmbtu/hr

Area heated: 67,938 sqft

Fuel consumed per year: 380 cords

This component calculates the potential change in heating oil usage from the installation of new cordwood boilers in non-residential buildings (assumed to heat 30% of non-residential square footage).