Current system

See: Generation for more details of the current generation systems

Modeled transmission project

Capital cost (total): $16,368,836

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-10,127,388

Net lifetime savings: $-26,496,224

Benefit-cost ratio: -0.6

Nearest community: Selawik

Distance: 32 miles

Maximum savings: $0.03/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.