Modeled biomass cordwood project

Capital cost: $197,682

Lifetime energy cost savings: $60,045

Net lifetime savings: $-137,637

Benefit-cost ratio: 0.3

Proposed max capacity: 298,787 mmbtu/hr

Area heated: 7,647 sqft

Fuel consumed per year: 52 cords

This component calculates the potential change in heating oil usage from the installation of new cordwood boilers in non-residential buildings (assumed to heat 30% of non-residential square footage).