Current system

See: Generation for more details of the current generation systems

Togiak (quigmy river)

Present value of capital cost: $31,217,925

Lifetime energy cost savings: $5,595,560

Net lifetime savings: $-25,622,365

Benefit-cost ratio: 0.2

Proposed nameplate capacity: 432 kW

Expected yearly generation: 2,293,860 kWh/year

Phase: Reconnaissance

Upfront capital cost: $31,782,415

Estimated hydro penetration level: 76.41%

source: link

Togiak (kurtluk river)

Present value of capital cost: $16,023,996

Lifetime energy cost savings: $6,709,608

Net lifetime savings: $-9,314,388

Benefit-cost ratio: 0.4

Proposed nameplate capacity: 340 kW

Expected yearly generation: 1,805,353 kWh/year

Phase: Reconnaissance

Upfront capital cost: $16,313,746

Estimated hydro penetration level: 60.13%

source: link

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from the installation of new hydropower infrastructure. Requires that at least a reconnaissance-level hydropower study has been completed for the community.