Current system

See: Generation for more details of the current generation systems

Modeled transmission project

Capital cost (total): $12,141,071

Capital cost (cost per mile): $500,000/mile

Lifetime energy cost savings: $-4,043,442

Net lifetime savings: $-16,184,513

Benefit-cost ratio: -0.3

Nearest community: Eek

Distance: 24 miles

Maximum savings: $0.02/kWh

This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.