See: Generation for more details of the current generation systems
Modeled transmission project
Capital cost (total): $14,099,633
Capital cost (cost per mile): $500,000/mile
Lifetime energy cost savings: $-9,198,052
Net lifetime savings: $-23,297,685
Benefit-cost ratio: -0.7
Nearest community: Chignik Lake
Distance: 28 miles
Maximum savings: $0.09/kWh
This component calculates the potential cost savings through changes in the amount of diesel fuel used for electricity generation from connecting communities via transmission lines.